Question: 1 / 200

In the context of Site Reliability Engineering, what should be prioritized when drafting a postmortem report after an incident?

Identify responsible engineers and escalate to management.

Ensure that test cases are run successfully before releases.

When drafting a postmortem report after an incident within the framework of Site Reliability Engineering (SRE), the primary focus should be on learning from the event to prevent future occurrences and improve overall reliability. In this context, ensuring that test cases are run successfully before releases represents a proactive approach. It emphasizes the need for robust testing as a preventive measure to validate changes in the system and is critical in avoiding similar incidents in the future.

This approach aligns with the SRE principles of prioritizing reliability and continuous improvement. By focusing on test case success, the organization strengthens its change management process, ensures that potential issues are detected early, and reduces the risk of incidents that could disrupt services.

Other options, while potentially relevant in certain contexts, center more around reactive measures or procedural follow-up rather than the core focus of postmortem analysis, which is learning and improvement. For instance, identifying responsible engineers or escalating issues to management does not foster a culture of open learning and improvement. Establishing policies for immediate responses or following up with employees involved in changes may be important, but they do not address the more significant goal of improving the system through effective testing and validation. Hence, ensuring successful test cases before deployments is the most beneficial priority when creating a postmortem

Get further explanation with Examzify DeepDiveBeta

Follow up with employees who reviewed the changes.

Design a policy for immediate incident response calls.